SERBIA RAILWAY SECTOR MODERNIZATION PROJECT (SRSM) – Preparation of technical specifications (phase 2)

Ministarstvo građevinarstva, saobraćaja i infrastrukture

posle izbora

Ovaj akt još nije pregledao čovek. Nivo je procenjen mašinski prema pravilima i ne predstavlja naš stav.

Šta možete da uradite

Vrsta akta još nije određena. Pogledajte katalog akcija.

Ključni podaci

Oblast
Građevinarstvo, saobraćaj, infrastruktura
Vrsta dokumenta
Konkurs, oglas
Datum
2.11.2026.prvog uočavanja
Kako smo ocenili (rizik: 5 od 100)

Ocena je dobijena mašinski prema pravilima iz metodologije. Metodologija.

Nadležnostda li akt sme da se donese u tehničkom mandatu 5 od 30 Vezivanje budućnostitrajanje, vrednost, nepovratnost 0 od 30 Procedurarok, objava, plan, period posle izbora 0 od 25 Korisnikpodaci iz registara 0 od 15
  • resor iz izvora: infrastruktura
Prilozi (3)
  • REoI-SER-SRSM-CQ-CS-22-42-TA for technical specification for machinery - EXTENSION.pdf · arhiva · 8.342 znakova
    Izvučeni tekst
    EXTENSION OF DEADLINE FROM JANUARY 31 TO FEBRUARY 10, 2023 
    REQUEST FOR EXPRESSIONS OF INTEREST 
    
    Republic of Serbia 
    The Serbia Railway Sector Modernization Project (SRSM) 
    Project ID No. P170868 
    
    Assignment Title: 
    Technical Advisory for the preparation of Implementation Plan and Technical 
    Specifications for Procurement of Rail Heavy Duty Machinery 
    Reference No. SER-SRSM-CQ-CS-22-42 
    
    The International Bank for Reconstruction and Development (IBRD) launched the 
    Multiphase Programmatic Approach (MPA) to support the Government of Serbia (GoS) 
    in continuation of institutional, physical and operational modernization of the railway 
    sector in an integrated manner through providing financial support to Serbia Railway 
    Sector Modernization Project as part of the Multiphase Programmatic Approach to be 
    implemented in three overlapping phases over the ten-year period. 
    While the implementation of Phase 1 of the MPA is undergoing, the preparation of Phase 
    2 of the MPA is underway, within which the purchase of rail heavy duty maintenance 
    machinery is planned. 
    These Terms of Reference (ToR) relate to a consultancy firm for Technical Advisory on 
    preparing an Implementation Plan and Technical Specification for the Procurement of 
    Rail Heavy Duty Maintenance Machinery. MCTI, with the support of IZS, intends to 
    engage a highly qualified consultant to provide services more closely described below. 
    The objectives of the Services are to develop an implementation plan with cost estimates 
    and technical specifications for the rail heavy-duty maintenance machinery envisaged 
    for procurement as part of the second phase of the SRSM Project. 
    
    In short, the scope of work of the Consultant is to perform the following activities as a 
    part of the Services: 
    Activity 1: Inception which includes the following tasks: 
     
    Kick-off meeting, coordination, and agreement on the assignment with the key 
    stakeholders, including PIU, MCTI, IZS, World Bank and FDA, 
     
    Organization of the assignment’s inception (logistics, content, etc.) so that 
    subsequent activities can run smoothly. 
     
    Preparation of the detailed work plan and expert mobilization according to the 
    technical proposal; 
     
    Obtaining and reviewing previous studies, maintenance programs and 
    accompanying reports related to the conditions of the current conditions of the 
    maintenance machinery and interviews with IZS employees involved in the 
    maintenance process. 
    Activity 2: Preparation of Implementation Plan and Technical Specifications 
    Under Activity 2 the Consultant will include the preparation of an implementation plan as 
    the basis for the development of bidding documents as well as bidding procedure, 
    
    evaluation and contracting procedures and Technical Specifications and functional 
    requirements for Heavy Duty Maintenance Machinery 
     Sub-activity 2.1: preparation of Implementation Plan 
     Sub–Activity 2.2: preparation of Technical specifications 
    The intended commencement date is March 2023, but the actual commencement date 
    will be five days from the signature of the Contract. The period of implementation of the 
    contract will be 6 months starting from the commencement date. 
    The detailed Terms of Reference for the above referenced consulting services is posted 
    on the website of the Ministry of Construction, Transportation and Infrastructure (MCTI) 
    https://mgsi.gov.rs/cir/dokumenti/serbia-railway-sector-modernization-project-srsm-
    preparation-technical-specifications 
    Consultant qualification requirements 
    The Consultant firm will be selected in accordance with the CQS (Consultant's 
    Qualification Selection) method set out in the World Bank’s Procurement Regulations for 
    IPF Borrowers (July 2016, revised November 2017, August 2018 and November 2020). 
    The Consultant that obtains the highest score during evaluation of expressions of interest 
    will be invited to submit technical and financial proposals. 
    The assignment will require a qualified consulting company or joint ven
  • TOR_SER-SRSM-CQ-CS-22-42-TA for techcal specification for machinery.pdf · arhiva · 44.490 znakova
    Izvučeni tekst
    The Serbia Railway Sector Modernization (SRSM) Project 
    Phase 1 of the Multi-Phase Programmatic Approach 
    
    TERMS OF REFERENCES 
    for 
    Technical Advisory for the preparation of Implementation Plan and Technical 
    Specifications for Procurement of Rail Heavy Duty Machinery 
    
    January 2023 
    
    1. Background information 
    1.1 Beneficiary country: Republic of Serbia 
    Client: Ministry of Construction, Transport, and Infrastructure of the Republic of Serbia (MCTI). 
    Final Beneficiary: Infrastruktura železnice Srbije (Serbian Railway Infrastructure – IZS). 
    1.2 Relevant country background 
    The International Bank for Reconstruction and Development (IBRD) launched the Multiphase 
    Programmatic Approach (MPA) to support the Government of Serbia in the continuation of 
    institutional, physical and operational modernisation of the railway sector in an integrated manner 
    by providing financial support to Serbia Railway Sector Modernization Project as part of the 
    Multiphase Programmatic Approach to be implemented in three overlapping phases over the ten 
    years. 
    For financing Serbia Railway Sector Modernization Project, Phase 1 of the MPA (the Project), 
    IBRD and the Agence Francaise de Développement (AFD) jointly, granted to the Republic of 
    Serbia EUR 102 million loans to support enhancing the efficiency and safety of existing railway 
    assets and improving governance and institutional capacity of the railway sector. 
    The Project is managed by the Ministry of Construction, Transport and Infrastructure (MoCTI) 
    through the Project Implementation Unit (PIU) supplemented by the Project Implementation 
    Teams (PITs) in Railway Directorate (RD) and railway companies, respectively, Serbian Railway 
    Infrastructure (IZS), Serbia Voz (SV) and Serbia Cargo (SC). PITs act as subordinate 
    implementing agencies and provide technical support for specific Project subcomponents or 
    activities of the MPA that pertain to their area of expertise. Primary responsibility for Project 
    execution lies on PIU, which ensures that the Project development objectives are met. 
    The preparation of Phase 2 of the MPA is underway, within which the purchase of rail heavy duty 
    maintenance machinery is planned. These Terms of Reference (ToR) relate to a consultancy firm 
    for Technical Advisory on preparing an Implementation Plan and Technical Specification for the 
    Procurement of Rail Heavy Duty Maintenance Machinery. MCTI, with the support of IZS, intends 
    to engage a highly qualified consultant to provide services more closely described below. 
    1.3 General information 
    The position of Serbia in the European railway network is such that it forms part of the shortest 
    traffic line between West and South-East Europe. The length of the railway lines in the Republic 
    of Serbia is 3,438 km, of which 3,059 km are single-track and 288 km of double-track railway 
    lines. The total length of electrified railways is 1273 km. Railway lines on the territory of the 
    Republic of Serbia are more than one century old, and over half of all railway lines were built in 
    the 19th century. This network consists of railway lines which are part of the Pan-European 
    corridors, lines of international importance connecting Serbia with neighbouring countries, and 
    regional-local lines. 
    Due to its position on the geographic borderline between the East and the West, Serbia is often 
    referred to as a gateway to Europe. The important European Corridor X – the international highway 
    
    and railway corridor, part of the core TENT-T network through the Republic of Serbia (RoS), 
    provides excellent connections with Western Europe and the Middle East. 
    
    Figure 1: Position of Serbia with highlighted Rail Corridor X 
    The Serbian rail network includes a total of 5,247 switches of various types, 847 bridges in length 
    of 35.9 km, 4,816 culverts, 333 tunnels in length of 153 km and 2,121 level crossings with different 
    safety level systems. The designed condition of the railway network enables the traffic of railway 
    rollin
  • REoI-SER-SRSM-CQ-CS-22-42-TA for Techical specifications for machinery.pdf · arhiva · 8.278 znakova
    Izvučeni tekst
    REQUEST FOR EXPRESSIONS OF INTEREST 
    
    Republic of Serbia 
    The Serbia Railway Sector Modernization Project (SRSM) 
    Project ID No. P170868 
    
    Assignment Title: 
    Technical Advisory for the preparation of Implementation Plan and Technical 
    Specifications for Procurement of Rail Heavy Duty Machinery 
    Reference No. SER-SRSM-CQ-CS-22-42 
    
    The International Bank for Reconstruction and Development (IBRD) launched the Multiphase 
    Programmatic Approach (MPA) to support the Government of Serbia (GoS) in continuation 
    of institutional, physical and operational modernization of the railway sector in an integrated 
    manner through providing financial support to Serbia Railway Sector Modernization Project 
    as part of the Multiphase Programmatic Approach to be implemented in three overlapping 
    phases over the ten-year period. 
    While the implementation of Phase 1 of the MPA is undergoing, the preparation of Phase 2 
    of the MPA is underway, within which the purchase of rail heavy duty maintenance machinery 
    is planned. 
    These Terms of Reference (ToR) relate to a consultancy firm for Technical Advisory on 
    preparing an Implementation Plan and Technical Specification for the Procurement of Rail 
    Heavy Duty Maintenance Machinery. MCTI, with the support of IZS, intends to engage a 
    highly qualified consultant to provide services more closely described below. 
    The objectives of the Services are to develop an implementation plan with cost estimates and 
    technical specifications for the rail heavy-duty maintenance machinery envisaged for 
    procurement as part of the second phase of the SRSM Project. 
    
    In short, the scope of work of the Consultant is to perform the following activities as a part 
    of the Services: 
    Activity 1: Inception which includes the following tasks: 
    − 
    Kick-off meeting, coordination, and agreement on the assignment with the key 
    stakeholders, including PIU, MCTI, IZS, World Bank and FDA, 
    − 
    Organization of the assignment’s inception (logistics, content, etc.) so that 
    subsequent activities can run smoothly. 
    − 
    Preparation of the detailed work plan and expert mobilization according to the 
    technical proposal; 
    − 
    Obtaining and reviewing previous studies, maintenance programs and accompanying 
    reports related to the conditions of the current conditions of the maintenance 
    machinery and interviews with IZS employees involved in the maintenance process. 
    Activity 2: Preparation of Implementation Plan and Technical Specifications 
    Under Activity 2 the Consultant will include the preparation of an implementation plan as the 
    basis for the development of bidding documents as well as bidding procedure, evaluation and 
    
    contracting procedures and Technical Specifications and functional requirements for Heavy 
    Duty Maintenance Machinery 
    
    • Sub-activity 2.1: preparation of Implementation Plan 
    • Sub–Activity 2.2: preparation of Technical specifications 
    The intended commencement date is March 2023, but the actual commencement date will 
    be five days from the signature of the Contract. The period of implementation of the contract 
    will be 6 months starting from the commencement date. 
    The detailed Terms of Reference for the above referenced consulting services is posted on 
    the website of the Ministry of Construction, Transportation and Infrastructure (MCTI) 
    https://mgsi.gov.rs/cir/dokumenti/serbia-railway-sector-modernization-project-srsm-
    preparation-technical-specifications 
    
    Consultant qualification requirements 
    The Consultant firm will be selected in accordance with the CQS (Consultant's Qualification 
    Selection) method set out in the World Bank’s Procurement Regulations for IPF Borrowers 
    (July 2016, revised November 2017, August 2018 and November 2020). The Consultant that 
    obtains the highest score during evaluation of expressions of interest will be invited to submit 
    technical and financial proposals. 
    The assignment will require a qualified consulting company or joint venture that can 
    demonstrate extensive experience in technica
Tekst objave
SERBIA RAILWAY SECTOR MODERNIZATION PROJECT (SRSM) – Preparation of technical specifications (phase 2)

Dokumenti: 

REoI-SER-SRSM-CQ-CS-22-42-TA for technical specification for machinery - EXTENSION.pdf

TOR_SER-SRSM-CQ-CS-22-42-TA for techcal specification for machinery.pdf

REoI-SER-SRSM-CQ-CS-22-42-TA for Techical specifications for machinery.pdf
Povezani akti (8)

Izvor: mgsi.gov.rs Arhivirane kopije: 2.11.2026., 2.11.2026. U popisu od 2.11.2026.